A process instance is started on 5:48pm on 23 September. According to the process design, the process has a SLA of 10.0 hours.

With the Office Working Deadline plugin activated, the due date would not be a mere 5:48pm + 10 hours. It will be 5:48pm + 10 working hours.

On 23 September, there's only 12 minutes worth of working hours left. On 24 September, which is another new working day, we will get a full 8 hours from it. We have 8 hours and 12 minutes now and need another 1 hour 48 minutes. Effectively, the due date would be on 25 September, 9:48am.

...