Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Re-evaluate
    Re-evaluate the participant mapping for the current activity instance.
  • Re-evaluate assignment(s) for user
    Re-evaluate all assignments of a particular user.
  • Reassign user
    Reassign one of the assignee(s) of this activity instance to another user.
  • Complete
    Complete the activity instance as the current logged in user.

Activity State


English

When a new activity instance is created, the state will be set to open.not_running.not_started. In natural progression, the state will end with the state of closed.completed.

If the activity has a deadline triggered, the state will change to closed.terminated. If the process instance is aborted, then, the activity instance's state will change to closed.aborted.