Office Working Hour Deadline Plugin is an essential addition to the working environment where SLAs and deadlines are implemented.

This plugin will intercept and override how calculations are made by Joget when calculating due dates for SLAs and deadlines imposed on a process.

The Office Working Hour Deadline plugin takes the following into account during calculations:

  • Holidays
  • Working Hours
  • Working Days

Figure 1: Office Working Hour Deadline Properties

...

On 23 September, there's only 12 minutes worth of working hours left. On 24 September, which is another new working day, we will get a full 8 hours from it. We have 8 hours and 12 minutes now and need another 1 hour 48 minutes. Effectively, the due date would be on 25 September, 9:48am.