We have created the process in joget and in process we have defined some escalations so what is happening if activities get escalated and after escalation user ends original activity but the issue is escalation activities are not getting ended even user ends the original activities.So I want to know is this behavior normal or is there any way to end the activities.
Hi Experts,
We have created the process in joget and in process we have defined some escalations so what is happening if activities get escalated and after escalation user ends original activity but the issue is escalation activities are not getting ended even user ends the original activities.So I want to know is this behavior normal or is there any way to end the activities.
Thanks in advance