1
0
-1

I have a form in which the project start and finishing dates are chosen. I use these dates in the Calendar item in the userview. We are using Joget DX On-Demand.

The "To Date" values are shown one day earlier on the Calendar view. I couldn't find a variable to define include or exclude the "To Date".

Is this a known issue or am I doing something wrong?

Thanks in advance for your help.

Here are the screenshots of the form and the userview:

    CommentAdd your comment...

    1 answer

    1.  
      1
      0
      -1

      Thank you for reporting this issue. This fixed will be released in the next build, i.e. v7.0.9.

      1. Sebnem Kabadayi

        Thanks, the issue has been solved.

      CommentAdd your comment...