Hi, I assume that you are using the Run Process menu, since the process starts upon form submission. If you do not wish to tie the form submission to a process, you can try using the Form Menu instead.
Thank You Anders. Using Form menu instead of Run process solve the issue.
Hi,
Details: Form followed by bean shell activity and route to next assignment. We are submitting form by UI as well as API.
Problem Statement: API able to create record and start process successfully, but now if form submitted by UI 2 process has been initiated (one in prost processing bean Shell with record ID and 2nd by joget default on form submission.
Queries:
Flow: Form A → Activity → Route → Form B
Setup Details: Joget DX Enterprise (Version: 7.0.29 - build 29aa79a),
Appreciate your help.